On 11 March 2024, the Head of Government published Circular n° 03/2024 concerning the implementation of the Moroccan Offer for the development of the green hydrogen sector ("Circular").

The Circular applies to all investors wishing to develop projects integrating the entire value chain of green hydrogen production, including the components of renewable energy, electrolysis production, storage, transport and logistics, whether these projects are intended for import or export.


Contents

Main aspects

1. Governance of the green hydrogen sector

The Circular provides for the governance of the green hydrogen sector to be entrusted to the Moroccan Agency for Sustainable Energy (MASEN) and a dedicated steering committee.

MASEN's mission is to inform and support investors during the project validation process. As such, MASEN will receive initial investment applications and screen them before forwarding them to the steering committee. MASEN cannot itself carry out green hydrogen production projects on an industrial scale.

The steering committee will be responsible for approving the main agreements to be concluded with investors throughout the validation process.

The committee will also be responsible for monitoring project progress and developing the sector. It will be assisted by an investment committee.

Investors wishing to develop only one component of the hydrogen sector, or to invest downstream, can apply to the Regional Investment Centers or the Moroccan Investment Development Agency, and will benefit from the common investment regime.

2. The incentive scheme

The Circular does not introduce specific incentives for the hydrogen sector. Instead, it refers to existing advantages under the new investment charter.

Investors can benefit from tax and customs incentives (import duty and VAT for domestic and imported goods).

Dedicated industrial acceleration zones may also be created.

3. Land and dedicated infrastructures

The Circular mentions the identification by the State of 1 million hectares of land to support the green hydrogen sector, mainly in areas earmarked for solar and wind energy production under Law 13-09.

As green hydrogen is still an emerging sector, the State has decided to adopt a phased approach in order to maintain the flexibility required to adapt to changes in the sector, particularly technological, legislative, regulatory and market developments. The first phase aims to mobilize 300,000 hectares to be divided into plots of 10,000 to 30,000 hectares. The State also provides for the possibility of extension depending on projects' needs.

The government authorities in charge of the Interior and Economy and Finance are in charge for mobilizing land for the Moroccan Offer.

The Circular underlines the importance of developing the infrastructure necessary for green hydrogen such as power grids and port infrastructure, through the cooperation of various public actors and public-private partnerships.

French version


Copyright © 2024 Baker McKenzie. All rights reserved. Ownership: This site (Site) including all documentation and content (Content) is a Copyright © 2022 Baker & McKenzie. All rights reserved. Ownership: This documentation and content (Content) is a proprietary resource owned exclusively by Baker McKenzie (meaning Baker & McKenzie International and its member firms). The Content is protected under international copyright conventions. Use of this Content does not of itself create a contractual relationship, nor any attorney/client relationship, between Baker McKenzie and any person. Non-reliance and exclusion: All Content is for informational purposes only and may not reflect the most current legal and regulatory developments. All summaries of the laws, regulations and practice are subject to change. The Content is not offered as legal or professional advice for any specific matter. It is not intended to be a substitute for reference to (and compliance with) the detailed provisions of applicable laws, rules, regulations or forms. Legal advice should always be sought before taking any action or refraining from taking any action based on any Content. Baker McKenzie and the editors and the contributing authors do not guarantee the accuracy of the Content and expressly disclaim any and all liability to any person in respect of the consequences of anything done or permitted to be done or omitted to be done wholly or partly in reliance upon the whole or any part of the Content. The Content may contain links to external websites and external websites may link to the Content. Baker McKenzie is not responsible for the content or operation of any such external sites and disclaims all liability, howsoever occurring, in respect of the content or operation of any such external websites. Attorney Advertising: This Content may qualify as “Attorney Advertising” requiring notice in some jurisdictions. To the extent that this Content may qualify as Attorney Advertising, PRIOR RESULTS DO NOT GUARANTEE A SIMILAR OUTCOME. Reproduction: Reproduction of reasonable portions of the Content is permitted provided that (i) such reproductions are made available free of charge and for non-commercial purposes, (ii) such reproductions are properly attributed to Baker McKenzie, (iii) the portion of the Content being reproduced is not altered or made available in a manner that modifies the Content or presents the Content being reproduced in a false light and (iv) notice is made to the disclaimers included on the Content. The permission to re-copy does not allow for incorporation of any substantial portion of the Content in any work or publication, whether in hard copy, electronic or any other form or for commercial purposes.