Singapore: Passing of Electric Vehicles Charging Act 2022

In brief

The Electric Vehicles Charging Act 2022 ("Act") that seeks to regulate the provision of safe and reliable charging of Electric Vehicles ("EV") and the expansion of the EV charging infrastructure in Singapore was passed by Parliament in January 2023. The Act is expected to take effect in the second half of 2023.

Notably, the Act sets out a licensing regime for EV charging operators and also prescribes certification requirements that all EV chargers would have to meet before the chargers can be installed and used in Singapore.


Contents

In depth

The Act aims to ensure the safety, reliability and accessibility of EV chargers and the EV charging infrastructure. Two types of EV chargers are covered: (a) fixed chargers (including battery chargers and swap stations and pantograph chargers) and (b) non-fixed chargers. Chargers that are exclusively designed for charging non-EVs such as personal mobility devices, power-assisted bicycles, electric vessels, or electric aircrafts are not covered under the Act.

Upon commencement of the Act:

  • existing suppliers of EV chargers can continue to supply non-approved EV chargers for six months; and
  • existing EV charging operators can carry on operations without a licence for 12 months.

An elaboration of the key aspects of the Act is set out below on a non-exhaustive, high-level basis: 

  • Supply of EV chargers. All chargers supplied in Singapore must belong to a homologated model that meets the national charging standard - Technical Reference 25 ("TR25"). Failure to adhere to TR25 is an offence and imprisonment and financial penalties may be imposed. 
  • Advertisements of EV chargers. Non-approved EV charger models are prohibited from being advertised. The Land Transport Authority ("LTA") has the discretion to direct the advertiser to stop the further publication of the advertisement, disable access to the offending advertisement, or publish a corrective advertisement. 
  • Registration of EV chargers and ongoing compliance requirements. Any person who has control of an EV charger must apply to the LTA to register the EV charger before usage in Singapore. The registered responsible persons must thereafter ensure that the EV chargers are periodically inspected and certified as prescribed. There are also retention requirements for the certificates of fitness of the EV chargers. 
  • Licensing regime for EV charging operators. EV charging operators (businesses that provide EV charging services, such as hiring out a fixed EV charger, providing battery swapping services or renting out a non-fixed EV charger) will be required to obtain a licence in order to provide the service. In deciding whether an applicant should be granted a licence, the LTA will consider, amongst other factors, (a) whether the applicant is operating or is intending to operate more than one charging station in Singapore, and (b) the design and safety of the EV chargers/other equipment to be used by the applicant in undertaking the regulated activity in Singapore. The licence has a three year validity. Key licensing conditions include the purchase of public liability insurance, correcting EV charging service downtime issues within a specified duration and requiring the licensee to operate with interoperable open communication standards.
  • Mandatory provision of EV charging points. The Act mandates the provision of EV charging infrastructure by developers of specified building works and development owners that carry out certain types of electrical works. Developments with very small carparks (fewer than eight car and motorcycle lots) are exempt from this mandate.
  • Lower resolution thresholds for EV charger installations in Strata Units. Amendments to the Building Maintenance and Strata Management Act 2004 will lower the thresholds for management corporations ("MCST") to pass resolutions with a simple majority of votes for any proposal to install or uninstall EV chargers in strata-titled developments, provided that the lease contract between the MCST and EV charging operator does not exceed 10 years and the proposal does not draw down on MCST funds.

We would be happy to provide you with advice tailored to your specific needs on how to prepare for the commencement of this Act. For further information to discuss what this development might mean for you, please get in touch with your usual Baker McKenzie contact.

 

 

* * * * *

LOGO_Wong&Leow_Singapore

© 2022 Baker & McKenzie.Wong & Leow. All rights reserved. Baker & McKenzie.Wong & Leow is incorporated with limited liability and is a member firm of Baker & McKenzie International, a global law firm with member law firms around the world. In accordance with the common terminology used in professional service organizations, reference to a "principal" means a person who is a partner, or equivalent, in such a law firm. Similarly, reference to an "office" means an office of any such law firm. This may qualify as "Attorney Advertising" requiring notice in some jurisdictions. Prior results do not guarantee a similar outcome.


Copyright © 2024 Baker & McKenzie. All rights reserved. Ownership: This documentation and content (Content) is a proprietary resource owned exclusively by Baker McKenzie (meaning Baker & McKenzie International and its member firms). The Content is protected under international copyright conventions. Use of this Content does not of itself create a contractual relationship, nor any attorney/client relationship, between Baker McKenzie and any person. Non-reliance and exclusion: All Content is for informational purposes only and may not reflect the most current legal and regulatory developments. All summaries of the laws, regulations and practice are subject to change. The Content is not offered as legal or professional advice for any specific matter. It is not intended to be a substitute for reference to (and compliance with) the detailed provisions of applicable laws, rules, regulations or forms. Legal advice should always be sought before taking any action or refraining from taking any action based on any Content. Baker McKenzie and the editors and the contributing authors do not guarantee the accuracy of the Content and expressly disclaim any and all liability to any person in respect of the consequences of anything done or permitted to be done or omitted to be done wholly or partly in reliance upon the whole or any part of the Content. The Content may contain links to external websites and external websites may link to the Content. Baker McKenzie is not responsible for the content or operation of any such external sites and disclaims all liability, howsoever occurring, in respect of the content or operation of any such external websites. Attorney Advertising: This Content may qualify as “Attorney Advertising” requiring notice in some jurisdictions. To the extent that this Content may qualify as Attorney Advertising, PRIOR RESULTS DO NOT GUARANTEE A SIMILAR OUTCOME. Reproduction: Reproduction of reasonable portions of the Content is permitted provided that (i) such reproductions are made available free of charge and for non-commercial purposes, (ii) such reproductions are properly attributed to Baker McKenzie, (iii) the portion of the Content being reproduced is not altered or made available in a manner that modifies the Content or presents the Content being reproduced in a false light and (iv) notice is made to the disclaimers included on the Content. The permission to re-copy does not allow for incorporation of any substantial portion of the Content in any work or publication, whether in hard copy, electronic or any other form or for commercial purposes.