South Africa: Notice published for exclusion of solar PV installations from obtaining environmental authorisation and adoption of screening tool

In brief

The Ministry of Forestry, Fisheries and the Environment in South Africa has published a notice excluding the development and expansion of solar photovoltaic facilities, including any associated activity or infrastructure from the requirement to obtain environmental authorisation in terms of the National Environmental Management Act. Members of the public have 30 days from the date of publication (8 September 2022) to submit comments on the draft notice. The proposed exclusion for solar photovoltaic facilities presents opportunities for independent, small-scale power producers and is considered to be a step forward for the government in terms of its commitment to energy transition and to securing a reliable supply of clean energy in the country. Clara Hansen, Candidate Attorney, and Kieran Whyte, Partner and Head of the Energy Mining and Infrastructure Sector Group in Johannesburg, outline the details.


Contents

On 8 September 2022, the Minister of Forestry, Fisheries and the Environment, Barbara Creecy published a notice excluding the development and expansion of solar photovoltaic facilities, including any associated activity or infrastructure from the requirement to obtain environmental authorisation in terms of the National Environmental Management Act 107 of 1998 (NEMA). 

Section 24(2)(e) of NEMA authorises the Minister to exclude activities that are prohibited from commencing without obtaining environmental authorisations from the competent authority, from the requirement to obtain an environmental authorisation based on compliance with an environmental management instrument adopted in the prescribed manner. 

The activities that are subject to the exclusion relate to the development or expansion of facilities or infrastructure for the generation of electricity from a solar photovoltaic installation, where such a development or expansion falls within the scope of Listing Notice 1 or Listing Notice 2 of NEMA. This includes the development or expansion of facilities or infrastructure for the generation of electricity from a renewable resource, where the electricity output is between 10 megawatts to 20 megawatts or more, excluding where such expansion of facilities or structure is for photovoltaic installations, and occurs within an urban area. 

The exclusion proposed by the notice will apply where the proposed development or expansion of a solar photovoltaic installation, including any associated activities, occur in areas of medium or low environmental sensitivity and are confirmed to be such by the site sensitivity verification. An exception is made for linear infrastructure, which is necessary and that forms an integral part of such activity, in which case such infrastructure can be in areas of very high or high, medium or low environmental sensitivity. The site sensitivity verification must be undertaken on the site on which the development or expansion is proposed to take place, by a specialist who demonstrates expertise in the field for which they are undertaking the verification. 

At least 15 days prior to the expected commencement date of the proposed development or expansion, such expansion or proposed development must be registered or re-registered with the competent authority. The registration will expire if construction does not commence within three years of the date on which the competent authority registered the proposed development or expansion. Re-registration of the facility and infrastructure is required when there is a change of ownership of a registered solar photovoltaic installation, which occurs prior to the completion of construction, and the development footprint of the facility and infrastructure is to be changed and would fall outside of the verified buffer. It should be noted that the intention of the notice is not that the site sensitivity verification and the report are to be undertaken for the entire site, but just for the area that has not been assessed. A re-registration is required to update the information on the records of the competent authority and to ensure that the new owner declares its intention to implement the mitigation measures in the environmental management programme. 

Within 10 days of receipt of the correctly completed registration form and supporting documentation, the competent authority must register the proposed development or expansion and provide the applicant with a registration number. 

Applications for environmental authorisations for activities listed in Listing Notice 1 and Listing Notice 2, which are pending on the date of coming into effect of the notice, must be finalised in accordance with the procedures of the Environmental Impact Assessment  Regulations, the Renewable Energy Development Zone Notice or the Strategic Transmission Corridor Notice, or may be withdrawn. A valid environmental authorisation in the case of any associated activities necessary for the realisation of photovoltaic facilities is deemed to have been complied with and is regarded as fulfilling the necessary requirements in terms of NEMA. 

Members of the public have 30 days from the date of publication to submit comments on the draft notice. The proposed exclusion for solar photovoltaic facilities presents opportunities for independent, small-scale power producers and is a step forward for the government in terms of its commitment to energy transition and to securing a reliable supply of clean electricity in the country.

Contact Information

Copyright © 2024 Baker & McKenzie. All rights reserved. Ownership: This documentation and content (Content) is a proprietary resource owned exclusively by Baker McKenzie (meaning Baker & McKenzie International and its member firms). The Content is protected under international copyright conventions. Use of this Content does not of itself create a contractual relationship, nor any attorney/client relationship, between Baker McKenzie and any person. Non-reliance and exclusion: All Content is for informational purposes only and may not reflect the most current legal and regulatory developments. All summaries of the laws, regulations and practice are subject to change. The Content is not offered as legal or professional advice for any specific matter. It is not intended to be a substitute for reference to (and compliance with) the detailed provisions of applicable laws, rules, regulations or forms. Legal advice should always be sought before taking any action or refraining from taking any action based on any Content. Baker McKenzie and the editors and the contributing authors do not guarantee the accuracy of the Content and expressly disclaim any and all liability to any person in respect of the consequences of anything done or permitted to be done or omitted to be done wholly or partly in reliance upon the whole or any part of the Content. The Content may contain links to external websites and external websites may link to the Content. Baker McKenzie is not responsible for the content or operation of any such external sites and disclaims all liability, howsoever occurring, in respect of the content or operation of any such external websites. Attorney Advertising: This Content may qualify as “Attorney Advertising” requiring notice in some jurisdictions. To the extent that this Content may qualify as Attorney Advertising, PRIOR RESULTS DO NOT GUARANTEE A SIMILAR OUTCOME. Reproduction: Reproduction of reasonable portions of the Content is permitted provided that (i) such reproductions are made available free of charge and for non-commercial purposes, (ii) such reproductions are properly attributed to Baker McKenzie, (iii) the portion of the Content being reproduced is not altered or made available in a manner that modifies the Content or presents the Content being reproduced in a false light and (iv) notice is made to the disclaimers included on the Content. The permission to re-copy does not allow for incorporation of any substantial portion of the Content in any work or publication, whether in hard copy, electronic or any other form or for commercial purposes.