Malaysia: Sungai Udang Waste-to-Energy Project RFP

In brief

The Malaysian Ministry of Housing and Local Government has announced that the request for proposal (RFP) for a waste-to-energy project in Sungai Udang, Malacca ("WtE Project") will be released on 18 February 2021. Consistent with the previous RFP for the waste-to-energy project located in Bukit Payong that was issued in August 2020, the WtE Project will be carried out on a public-private partnership basis. We understand the WtE Project is near to a current sanitary landfill and the driver is to reduce waste disposal rate at the landfill.

The WtE Project is the second of the six proposed waste-to-energy projects that the federal government of Malaysia is planning to develop by 2021.


Contents

RFP Conditions

In order to participate in the WtE Project, bidders are required to meet the following conditions:

  • at least 51% of the equity in the project company is owned by local Malaysian company;
  • experience in solid waste management, including solid waste treatment facilities and landfills;
  • experience in operating solid waste management facilities using technology akin to the technology stated in the RFP, with a minimum capacity of 800 metric tonnes-per-day;
  • the proposed technology has a track record of at least 3 years; and
  • the proposed technology can operate at least 8,000 hours a year.

Bidders are not required to attend a mandatory site visit and briefing session prior to the purchase of the RFP as compared to the approach taken for the Bukit Payong project. The RFP is available for purchase from 18 February 2021 to 10 March 2021 at a price of RM 10,000 from the office of the Department of National Solid Waste Management. The RFP submission will close on 10 May 2021.

Considerations for potential bidders

The following are some key issues that potential bidders should consider and be aware of in participating in the WtE Project:

  • The concession agreement and power purchase agreement to be entered into by the project company with the respective counterparties are likely to be non-negotiable, an approach which is common in Malaysia for projects of such nature. Bidders should scrutinize the interface issues between the concession agreement and the power purchase agreement to assess the risks arising from the gaps between these two key project documents.
  • Further, there may be bankability issues that may concern international financiers, for instance whether direct agreements with lenders are permitted and whether these agreements include or contain adequate termination payments and specific government force majeure relief. That said, local financiers are typically less adverse to such risks and are well placed to finance such projects.
  • While there is no site acquisition risk as the site should be provided by way of land lease from the Government, the Government will not provide any study including on waste properties, ground conditions, soil investigation and power system studies so proper site studies and investigations should be conducted and given the restrictions in travelling in view of the COVID-19 pandemic, the use of local consultants should be preferred. Site risk, including underground risks, will likely be assumed by the project company even though the site might be owned by the federal government of Malaysia or relevant State government.
  • There may also be resistance and challenges by various interested parties such as the local community and NGOs in relation to environmental, social and health issues. It is prudent to perform due diligence on the proximity of the site to residences and commercial buildings and to be prepared for community engagement to mitigate potential resistance and challenges in this regard.
  • In view of the ongoing COVID-19 situation in Malaysia, bidders should take into account delays that could be caused by the movement restrictions on supply chain, including importation of materials and delays in production due to reduced operating capacity of plants, and construction activities. The specific force majeure provisions in the upstream project documents with the government and with downstream contractors will need to be carefully thought through on the extension of time of completion and/or cost relief regime allocation.

Click here to access the Chinese Version.

LOGO Malaysia_Wong & Partners_KualaLumpur

This client alert was issued by Wong & Partners, a member firm of Baker McKenzie International, a global law firm with member law firms around the world. In accordance with the common terminology used in professional service organizations, reference to a "partner" means a person who is a partner or equivalent in such a law firm. Similarly, reference to an "office" means an office of any such law firm. This may qualify as "Attorney Advertising" requiring notice in some jurisdictions. Prior results do not guarantee a similar outcome. 

Contact Information

Copyright © 2023 Baker & McKenzie. All rights reserved. Ownership: This documentation and content (Content) is a proprietary resource owned exclusively by Baker McKenzie (meaning Baker & McKenzie International and its member firms). The Content is protected under international copyright conventions. Use of this Content does not of itself create a contractual relationship, nor any attorney/client relationship, between Baker McKenzie and any person. Non-reliance and exclusion: All Content is for informational purposes only and may not reflect the most current legal and regulatory developments. All summaries of the laws, regulations and practice are subject to change. The Content is not offered as legal or professional advice for any specific matter. It is not intended to be a substitute for reference to (and compliance with) the detailed provisions of applicable laws, rules, regulations or forms. Legal advice should always be sought before taking any action or refraining from taking any action based on any Content. Baker McKenzie and the editors and the contributing authors do not guarantee the accuracy of the Content and expressly disclaim any and all liability to any person in respect of the consequences of anything done or permitted to be done or omitted to be done wholly or partly in reliance upon the whole or any part of the Content. The Content may contain links to external websites and external websites may link to the Content. Baker McKenzie is not responsible for the content or operation of any such external sites and disclaims all liability, howsoever occurring, in respect of the content or operation of any such external websites. Attorney Advertising: This Content may qualify as “Attorney Advertising” requiring notice in some jurisdictions. To the extent that this Content may qualify as Attorney Advertising, PRIOR RESULTS DO NOT GUARANTEE A SIMILAR OUTCOME. Reproduction: Reproduction of reasonable portions of the Content is permitted provided that (i) such reproductions are made available free of charge and for non-commercial purposes, (ii) such reproductions are properly attributed to Baker McKenzie, (iii) the portion of the Content being reproduced is not altered or made available in a manner that modifies the Content or presents the Content being reproduced in a false light and (iv) notice is made to the disclaimers included on the Content. The permission to re-copy does not allow for incorporation of any substantial portion of the Content in any work or publication, whether in hard copy, electronic or any other form or for commercial purposes.