On 2 February 2025, Ministerial Resolution No. 034-2025-MINEM/DM ("Resolution") was published. It amends Ministerial Resolution No. 104-2024-MINEM/DM, which approved the administrative measures under which the prior consultation process for the electricity subsector must be carried out.


Contents

In more detail

The following are the main provisions of the Resolution:

  • Administrative Measure Nos. 8 and 9, approved through Ministerial Resolution No. 104-2024-MINEM, were modified, as well as when the prior consultation should be conducted.
Resolution No. 104-2024-MINEM Resolution
Administrative Measure
No. 8
Timing of the prior consultation process Administrative Measure
No. 8
Timeliness of the prior consultation process
Conformity of the final-stage engineering of the project corresponding to the concession contract subscribed as a result of the private investment promotion process conducted by Proinversión, or the equivalent act provided for in the aforementioned contract Prior to the issuance of the final engineering conformity of the project corresponding to the concession contract or the equivalent act provided for in the aforementioned contract Granting of the definitive transmission concession of the project corresponding to the concession contract, subscribed as a result of the private investment promotion process or public bidding Once the citizen participation plan or the terms of reference have been approved by the competent environmental authority, according to the environmental study applicable to the project, the prior consultation process must be concluded before the approval of the environmental management instrument.
Administrative Measure
No. 9
Timeliness of the prior consultation process Administrative Measure
No. 9
Timeliness of the prior consultation process
Approval of the feasibility of the projects included in the National Rural Electrification Plan Before approving the feasibility of the project Declaration by the General Directorate of Rural Electrification (Dirección General de Electrificación Rural (DGER)) of the viability of the investment project” (i.e., the DGER makes the declaration of viability) Before the project is declared feasible

 

  • Additionally, the following were specified:
  1. For Administrative Measure No. 8, the guidelines to be approved must state that the General Directorate of Electricity shall request the competent environmental authority to submit the corresponding documentation where the stakeholders identified within the area of direct and indirect influence of the investment project are verified.
  2. For Administrative Measure No. 9, the DGER will send the corresponding documentation contained in Report No. 2 of the pre-investment study, for the start of the consultation process prior to the projects proposed by the DGER.
  3. Projects that have not commenced construction and are currently being processed by the General Office of Social Management will be handled by that office in accordance with the administrative measures established in Ministerial Resolution No. 104-2024-MINEM.
  • Likewise, the Resolution provides for the publication of the draft directive that approves the "Guidelines for the implementation of the prior consultation processes in the electricity subsector." The directive's purpose is to establish the guidelines that regulate the actions to be carried out within the framework of the evaluation and implementation of the prior consultation process in the electricity subsector.
  • Interested parties have until Tuesday, 12 February 2025, to submit comments or contributions to the draft directive through the Ministry of Energy and Mines, located at Av. Las Artes Sur N.º 260, district of San Borja, or by email to lineamientoscpe@minem.gob.pe.

*****

We hope this information is of relevance to you and your company. Please do not hesitate to contact us if you require any advice in this regard.

Click here to read the Spanish version.

 

LOGO_Peru Estudio Echecopar_Lima

© 2025 Estudio Echecopar. All rights reserved. Estudio Echecopar is a member firm of Baker & McKenzie International, a Swiss Verein with member law firms around the world. In accordance with the common terminology used in professional service organizations, reference to a "partner" means a person who is a partner, or equivalent, in such a law firm. Similarly, reference to an "office" means an office of any such law firm. This may qualify as "Attorney Advertising" requiring notice in some jurisdictions. Prior results do not guarantee a similar outcome.


Copyright © 2025 Baker & McKenzie. All rights reserved. Ownership: This documentation and content (Content) is a proprietary resource owned exclusively by Baker McKenzie (meaning Baker & McKenzie International and its member firms). The Content is protected under international copyright conventions. Use of this Content does not of itself create a contractual relationship, nor any attorney/client relationship, between Baker McKenzie and any person. Non-reliance and exclusion: All Content is for informational purposes only and may not reflect the most current legal and regulatory developments. All summaries of the laws, regulations and practice are subject to change. The Content is not offered as legal or professional advice for any specific matter. It is not intended to be a substitute for reference to (and compliance with) the detailed provisions of applicable laws, rules, regulations or forms. Legal advice should always be sought before taking any action or refraining from taking any action based on any Content. Baker McKenzie and the editors and the contributing authors do not guarantee the accuracy of the Content and expressly disclaim any and all liability to any person in respect of the consequences of anything done or permitted to be done or omitted to be done wholly or partly in reliance upon the whole or any part of the Content. The Content may contain links to external websites and external websites may link to the Content. Baker McKenzie is not responsible for the content or operation of any such external sites and disclaims all liability, howsoever occurring, in respect of the content or operation of any such external websites. Attorney Advertising: This Content may qualify as “Attorney Advertising” requiring notice in some jurisdictions. To the extent that this Content may qualify as Attorney Advertising, PRIOR RESULTS DO NOT GUARANTEE A SIMILAR OUTCOME. Reproduction: Reproduction of reasonable portions of the Content is permitted provided that (i) such reproductions are made available free of charge and for non-commercial purposes, (ii) such reproductions are properly attributed to Baker McKenzie, (iii) the portion of the Content being reproduced is not altered or made available in a manner that modifies the Content or presents the Content being reproduced in a false light and (iv) notice is made to the disclaimers included on the Content. The permission to re-copy does not allow for incorporation of any substantial portion of the Content in any work or publication, whether in hard copy, electronic or any other form or for commercial purposes.